Deck The Grid: Festive Reflections On 2025's Real Estate Reform In The Energy Sector

KL
Herbert Smith Freehills Kramer LLP

Contributor

Herbert Smith Freehills Kramer is a world-leading global law firm, where our ambition is to help you achieve your goals. Exceptional client service and the pursuit of excellence are at our core. We invest in and care about our client relationships, which is why so many are longstanding. We enjoy breaking new ground, as we have for over 170 years. As a fully integrated transatlantic and transpacific firm, we are where you need us to be. Our footprint is extensive and committed across the world’s largest markets, key financial centres and major growth hubs. At our best tackling complexity and navigating change, we work alongside you on demanding litigation, exacting regulatory work and complex public and private market transactions. We are recognised as leading in these areas. We are immersed in the sectors and challenges that impact you. We are recognised as standing apart in energy, infrastructure and resources. And we’re focused on areas of growth that affect every business across the world.
As the lights twinkle and the year wraps up, we're unwrapping the big changes that shaped the UK energy sector in 2025 - from grid reforms to planning shake-ups - and what they mean for 2026.
United Kingdom Energy and Natural Resources
William Turnbull’s articles from Herbert Smith Freehills Kramer LLP are most popular:
  • in United Kingdom
Herbert Smith Freehills Kramer LLP are most popular:
  • within Energy and Natural Resources, Transport and Environment topic(s)

As the lights twinkle and the year wraps up, we're unwrapping the big changes that shaped the UK energy sector in 2025 - from grid reforms to planning shake-ups - and what they mean for 2026.

As the year draws to a close and the festive season approaches, we're taking stock of the legal developments that have shaped the UK energy landscape in 2025— spanning grid connections, planning, real estate and construction.

It's been a transformative year, driven by the UK's net zero ambitions and major infrastructure reforms. From the Government's Clean Power 2030 Action Plan to grid connection reforms and planning changes for energy projects, these developments are already influencing how and where investment flows.

Here are the key highlights – and what they mean for 2026:

1. Clean Power 2030: Connections Reform

Last year's Christmas present to the UK energy industry was the Government's Clean Power 2030 Action Plan, gifted on 20 December 2024. Its ambition is to ensure clean power sources generate at least as much power as Great Britain consumes, with 95% of generation coming from clean sources by 2030. The plan sets out the capacity range anticipated for each in-scope technology type needed to achieve the 2030 target and consolidates existing and new actions to be taken across the energy sector to achieve this goal.

2025 was a key year for investors in power projects and infrastructure in Great Britain, with investment being called for at pace and a wave of reforms being introduced across the sector, to achieve the Government's clean energy goals in 2030 and beyond. Amongst many other changes, the industry has seen changes to the Contracts for Difference and Capacity Market schemes, new support being introduced for long-duration electricity storage, zonal pricing being ruled out as part of the Government's Review of Market Arrangements (REMA) process and major reforms to the grid connections process.

This year's most in-demand Christmas present will, for many, be the publication of the outcomes of the Gate 2 to Whole Queue process, which NESO has committed to delivering this week. Connections reform has been a major feature of 2025, with the previous "first come, first served" application process being replaced by a "first ready and needed, first connected" process with gated application windows. Developers with pre-energisation grid connection offers were required to re-apply for firm Gate 2 connections in August 2025. This week, developers will be told whether their project will receive a firm Gate 2 connection offer, which phase of queue allocation they have been sorted into, whether they have protected status and if they have already passed detailed checks.

For those projects which receive Gate 2 outcomes, they will need to await further details of their connection date, point of connection and costs, in 2026. For those which don't receive Gate 2 offers, 2026 will involve a re-examination of project viability and, for viable projects, submission of an application in the first enduring Gate 2 application window (not expected until at least Q2 2026). Developers seeking import connections for electricity demand should also be aware that 2026 is likely to bring further connections reforms for demand. Prioritisation of strategic demand projects, such as data centres in AI Growth Zones, is expected to be introduced amongst other measures (see our article on AI Growth Zones here).

NESO's proposed pathways for the Strategic Spatial Energy Plan (the SSEP), the successor to the Clean Power 2030 Action Plan, are expected in 2026. Several months of delay have recently been announced so government adoption of the final plan may now slip to 2027. The SSEP will become the longer-term GB-wide spatial energy plan for large-scale electricity and hydrogen generation and storage to 2050. It will forecast energy supply and demand characteristics and map potential zonal locations, quantities and types of generation and storage. As the SSEP will replace the Clean Power 2030 Action Plan as the basis on which projects seeking a grid connection are deemed "needed" going forward, its publication will impact on where projects can be developed.

2. Planning and Infrastructure Bill

The latter part of 2025 has seen much focus (in planning circles at least) on the course of the Planning and Infrastructure Bill through Parliament and it seems we are due a late Christmas present with the Bill set to receive royal assent and parts of it to start coming into force before the end of the year. The changes to the pre-application consultation and acceptance stages for Nationally Significant Infrastructure Projects in particular will hopefully lead to quicker pre-application periods, with a focus on meaningful consultation and good quality applications and less time incurred in undertaking unnecessarily precautionary or prescriptive extra work. Guidance is awaited as to what will replace statutory consultation – something else to look forward to in 2026.

There is more of a question over how effective those parts of the Bill relating to nature recovery and the introduction of Environmental Delivery Plans will be, and this will be something to watch in the upcoming year.

Heading into 2026, the combination of the Planning and Infrastructure Bill changes (with clarity as to consultation requirements), the imminent designation of the revised Energy National Policy Statements, and the outcomes from the Gate 2 process, should all see greater certainty for the consenting and delivery of energy projects, in line with the Clean Power Action Plan 2030.

3. Proposed reforms for electricity network infrastructure

With NESO forecasting that twice as much transmission infrastructure will be needed by 2030 as in the past decade, and up to 460,000 km of additional distribution cabling by 2050, we welcomed the Government's July 2025 consultation on proposed reforms to streamline land rights and access processes for electricity network infrastructure – as these have historically caused costly delays.

The consultation places a particular emphasis on necessary wayleaves (a statutory right allowing electricity companies to install and maintain power lines on private land, even without the landowner's agreement). Key proposals include extending the standard term of a necessary wayleave from 15 to 40 years, requiring landowners or occupiers to provide reasons when serving a Notice to Remove, and supporting the use of virtual hearings.

These proposals, which the government intends to deliver over the next 18 months, represent a step forward but are not transformative. Our "Christmas wish list" for reform includes amending the Electricity Act 1989 to restrict successor landowners from serving a Notice to Remove during the term of a necessary wayleave, thereby preventing repeated applications after ownership changes. Additionally, establishing a definitive registration regime for necessary wayleaves and clarifying ambiguities in existing law would help ensure greater transparency and legal certainty for both network operators and landowners.

4. Procurement of new technology projects

The ideal position for both Christmas presents and the financing of power projects is a full wrap. However, for sub-optimally shaped presents (hello wine bottle) and new technology projects – a full wrap can be difficult to achieve (and may not be worth the effort).

A full (technology) wrap promises single point accountability when proprietary process technology sits at the heart of a project. In its purest form, your EPC contractor wraps the licensor and the black box process, taking responsibility for design integration, procurement, construction, commissioning and whole of facility performance. Acceptance is tied to minimum performance thresholds, and failure triggers capped delay and performance liquidated damages, with the potential for make good windows and claw back mechanisms to soften the edges.

Market reality, however, often points to a partial wrap (think a semi-eaten chocolate orange). Here, the EPC contractor procures and integrates the technology but is only liable for technology failures to the extent it can recover those damages from your technology partner. The contractor may be entitled to rely on the adequacy of the process design, while still carrying overall design coordination risk and the burden of proving that failures stem from the black box.

This model can work if the drafting is crisp: clear interface matrices; defined acceptance criteria; targeted LDs; practical make good pathways; and robust IP infringement indemnities. Collateral warranties, third party rights or tripartite arrangements can give the EPC standing to pursue licensor remedies for as long as it bears performance risk. The price is negotiation intensity and longer bid cycles—so if a wrap is the goal, signal it early.

As explored in our ICLG Construction & Engineering Law 2025 chapter, new technology complicates everything. First of a kind (FOAK) risk profiles, sparse operating data and tight licensor liability postures can make a meaningful wrap economically inefficient or simply unavailable.

That is where disaggregated, unbundled and/or collaborative approaches earn their keep. Keeping all design "under one roof" with the technology licensor leading FEED and ongoing design coordination can reduce interface risk and bring the black box owner closer to delivery decisions, even as the client retains more exposure.

Our experience in 2025 is that incentivised contracting and, in select cases, equity participation by delivery partners can better align interests, but they demand careful governance to manage conflicts. Do not expect insurance to backfill the gap for novel processes—underwriting needs data that may not exist. For sponsors and lenders, the discipline is the same: protect continuity and underwrite the gaps. Escrow of critical know how and licence continuity on licensor insolvency or withdrawal are essential.

Where risk transfer stops, contingency and sponsor support begin. The question is not whether a full wrap is "best", it is whether the chosen architecture consciously prices delay, performance and make good liabilities and allocates them to the party best able to manage them.

In 2026, the winning strategies will be early clarity on wrap intent, disciplined back to backs where needed, and design leadership that keeps the black box from becoming a black hole.

5. UK district heating networks

2025 has seen Ofgem step into its new role as consumer advocate and redress provider for heat networks in Great Britain. The countdown is now on: full regulatory rules, including Ofgem's enforcement powers and initial consumer protections, will come into force on 27 January 2026, with full compliance expected by early 2027.

As we approach the end of the year, as we discussed in our podcast on heat networks, landlords and developers would be wise to take stock and future-proof their projects. Key steps include reviewing their properties alongside both planned and existing heat networks. Where developments involve, or will involve, heat networks, reviewing the proposals against the forthcoming technical standards, ensuring metering and billing systems are ready to deliver transparent, consumption-based charges, and preparing governance structures for Ofgem registration and reporting.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

[View Source]

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More